Ford, Dagenham Diesel Centre
SDC Construction
Period : 46 weeks
Value : £550k
Construction of main fire wall to dissect main diesel centre. Wall
constructed to 4hr fire rating, designed with manufacturer to withstand
ambient wind loadings 14m overall height over 200 l/m. Various
facility offices over and above main contact works.
|
|